Mana Badi Nadu Nedu - Payment Procedure for Centralized Procurement items in Implementation of the MBNN Program – certain procedural guidelines
It has been directed the Head Masters and Mandal Engineers to place the indents
for the materials of centralized procurement such as Dual Desk Benches, Teacher
tables, Almarahs, Green Chalk Boards, Fans, Paintings and Sanitary ware. The
same has been done by the HM s and Mandal engineers and the suppliers started
supplying the material to school sites.
2. In this context, it is informed to the suppliers to give invoices to the HM s
for material they supplied at school level. After supplying the material, the
suppliers shall upload the invoices in STMS through the logins given to them.
Once the suppliers upload the invoices the same will be shown in HM s login.
After receipt of the material by HM, the HM shall select the invoice in STMS
which was already uploaded by the supplier and upload the same to Mandal
engineer. Before uploading the invoice, the HM shall ensure that the material is
received in good condition. Along with the invoice the HM also shall upload two
to four photographs of the material/painting supplied by the supplier. If the HM
is not satisfied the same shall be recorded and uploaded with specific comments
why the HM is not satisfied.
3. After the HM uploads the invoice, the Mandal engineer shall see the same
invoice in his login and he shall visit the school and take measurements and
check for the specifications and standards and record in M-book and upload the
same in STMS, recommending for payment. The Mandal engineer shall upload
the invoice along with the M book number, date of his visit, date of recording,
and validate the details of invoice like numbers, rate, total amount etc. If the
quality or specification is not as per specification in contract document, the same
shall be rejected and the same shall be recorded while uploading the invoice and
bill. The Mandal engineer also capture the photos of his visit to the material from
school site. While uploading the photo the longitude and latitude of the school
site will be uploaded automatically.
4. In case of dissatisfaction or rejection either by HM or Mandal engineer the
same shall be sent to the log in of the Executive Engineer APEWIDC. Then the EE
shall visit the school site and take a decision either to reject the material or
accept the material. On rejection, the invoice will be sent back to the supplier
with reasons of rejection. In case the material is accepted by the EE APEWIDC,
the same shall be pushed to FAO in APC s office. The FAO shall check whether
the photos are appropriate and the invoices are appropriate and upload the same
to APC. The APC shall then upload the bills to CFMS for arrangement of
payments to the suppliers directly to go to the bank account of suppliers.