School Education dept – Mana Badi Nadu Nedu – Ceiling for the materials and Labour Charges for Phase – II

Sub: School Education dept - Mana Badi Nadu Nedu-Ceiling for the materials and
Labour Charges for Phase - II- Issued - Regarding.
1. G.O.Ms No. 87 of the School Education (Prog-I) Department dated 30-

Ref: -

1-2019.

2. G.O. Ms No 22 of the school education (Prog II) Department dated 06-05-
2020.

3. G.O.MS No. 27 of the School Education (Prog-I) Departmet dated
30.03.2021.

In the 1st Phase of Mana Badi Nadu Nedu , it is learnt that the labourers and
vendors have insisted to pay higher rates than local market price, citing reasons that it
is Government work.ln some places labor and vendors have formed as a pressure
group and have demanded exorbitant rates.

In the community contract system it is expected that the Parent Committee
members, HM, Local Engineer shall negotiate and bargain for less rates compared to
market rates as it is a public work which is beneficial to students of the Village/Ward.

In this context, attention of all the District Educational Officers, Additional

Project C0ordinators and Executive Engineers of all the implementing agencies of
Mana Badi Nadu Nedu Phase I1, program in this State is invited to the references
cited above and they are requested to follow the Suggested normal Market rates of
Material and Labor Charges for Phase-II works which are to be executed by the
Parents Committee through Community Contract system,s0 as to not giv
for misuse of funds by Paying higher rates. In case of interior pockets, hilly terrains,
the maximum permissible market rates may be adopted.

any scope

The parent committees shall explore market rates and negotiate even

below normal rates. In any case permissible maximum rates cannot be exceeded.
Hence, it is requested to adopt the suggested normal market rates of material and
Labour charges as shown in the Annexure-I (for Material Rates) and Annexure-II
for Labour Rates) enclosed.









If the Market Rates of Material and Labour Charges of a given Mandal

are beyond Suggested Maximum Market rates given in Annexure I and II,then they
shall be approved by District level tender committee headed by the Joint Collector
constituted as per GO MS No 27 date 30.03.2021.