Mana Badi Nadu Nedu, Phase-II- Ensure that the instructions should be followed while implementing the program

Government vide reference read above, accorded Administrative sanction for
improving Infrastructure facilities in 22,344 Schools and other Educational institutions
with a total budget outlay of Rs.8000 Crores under Phase 2 of Mana Badi Nadu Nedu
program.
It is proposed to complete all the Nadu Nedu components and keep the schools ready
by 12th June 2023. During the coming two months the following activities will be started.
I. Roof repairs and Ceiling repairs.
II. Supply and installation of furniture.
Il. Major and Minor Repairs.
IV.Repairs and completion of Toilets.
V. Repairs and construction of Kitchen Sheds.
Except construction of ACRs and Compound Walls all other Nadu Nedu
components are targeted for completion by 12th June 2023.
The following activities should be attended to by all the Head Masters of Phase-ll




Nadu Nedu Schools to ensure proper execution and completion of Nadu Nedu works.
All the CPM (central procurement material) items should be received by the Head
Master or his/her authorized representative and two Parent Committee members.
Once the Head Masters gave readiness for any CPM material such material has to
be accepted, rejection can be done only on account of poor quality or short supply.