Mana Badi Nadu Nedu - Certain issues pending pertains to painting works at District level - instructions issued

Sub: Mana Badi Nadu Nedu - Certain issues pending pertains to painting works
at District level - instructions issued regarding.
Issues raised by the M/S. Berger in weekly video conference held on 25.08.2021.

Ref:

*****

Nadu-Nedu, Phase- program is taken up by the state Government to provide a
facelift to all the Government schools in the state and almost all the works are completed.

Further, it is noticed that some issues are pending at District level pertaining to

painting works and M/S Berger requested the following issues during weekly video

conferences:

1) In 574 Schools (list enclosed ) where Joint Measurements are taken up by M/S
erger team and Field Engineers. joint measurement value should be taken as
the final measurement and the same should be updated in STMS and recorded in

M-Book.



2) In 14 Schools (list enclosed) Field Engineer entered zero value and based on the
work done the actual joint measurement recorded should updated in the STMS

software as well as in M-Book record.

3) In 5,107 Schools (list Enclosed) Joint measurement need to be done and the
same should be updated in the STMS and record in M-Book.
4) Payment of Pending Demo Schools painting work done by M/S/. Berger should
be processed immediately.

The M/S Tata Consultancy limited is requested to reopen the schools list enclosed

with this circular duly facilitating to re-enter the painting details as per agreed quantities

in STMS, AE Login and raise FTOs for those balance adjustment invoices.

These instructions are issued to ensure timely completion and close of painting works.