Nadu Nedu works VC BY CM- Talking points
Talking points for the VC dated 07-05-2020:
1. Honorable CM during the VC on 5th April has instructed to complete
all the Nadu Nedu works under phase-I by end of July 2020.
2. Hence ground all the 9 components of all the school projects.
3. The District Collectors were instructed by the honorable CM to
review the progress with implementing agencies on weekly basis.
4. Hence the implementing agencies shall prepare weekly action plan
for completion of their targets.
Relaxations under para 3(XVI) of the G. O. Ms. No. 87, School Education
(Prog-II) Department dated 30-11-2019:Govt has issued GO Ms. No. 22
dated 06-05-2020 is issued with the following guidelines in fund
management:
1. All the school projects should be started except the school
projects which are in containment zone
2. A revolving fund to the extent of 15 % of the total project cost
will be released to the parent s committees. Generated RF will be
visible in AEE / Site Engineers login for approval and for further
submission to APC Samagra Shiksha. The APC SS shall approve
and push to CFMS for making payments to PC s bank account.
APC can select multiple FTO based on the size of the FTO file
which will be digitally signed, and APC can download FTO hard
copy for office purpose.
3. Once the 15 % revolving fund is received, the information should
be given to PC in their regular weekly meeting. The same shall
be recorded in minutes and books of accounts.
4. Now the revolving fund can be used by the PC for payments
towards labour, material and other expenses meant for
implementation of the MBNN project.
5. The vendor registration and collection of in-voices are dispensed
with. The PC can buy/purchase/procure by paying the money
through cheques directly to vendors or mastries from their